Location of facility – on plateau Vlašić mountain, about 15 km northwest from Travnik
Type o facility – Wind Power Plant
Installed capacity - up to 50 MW
Annual production - 126 GWh
Investment
Investments - 176 million KM
Financing - EIB and KfW loans, WBIF grant and EPBiH funds
Project status
Completed activities:
• Concession Agreement
• Feasibility Study With Environmental Impact Study
• Expropriation Study
• Consent In Principle For Connection - Elektroprenos
• Critical Habitat Assessment Study for the WPP Vlašić
• Preliminary Design WPP Vlašić
Activities in progress:
• Innovations in the technical part of the Feasibility Study
• On-site socio-economic survey involving consultations with landowners and land users, conducted by a KfW international consultant with local partners.