Location of the facility - the Drina River, area of the Bosnian-Podrinje Canton of Goražde
Type of facility – run of river power plant
Installed capacity - 60.48 MW
Annual generation - 236.80 GWh
Investment
Investment - BAM 270 million
Financing - Loans and funds of EPBIH
Project status
Preliminary design and Environmental Impact Study - 2013
Designer: Consortium / Energoinvest d.d. Sarajevo, IPSA Sarajevo and Poyry Energy GmbH Austria
Auditor: Zavod za vodoprivredu d.d. SarajevoGeological-geomechanical investigation works, geophysical tests, laboratory tests and creation of documentation for mission G1 - 2023
Designer: GeoAVAS d.o.o. Sarajevo
Auditor: GEO KONZALTING d.o.o. Sarajevo
Contractor: Subsidiary company GEOLP d.o.o. Kakanj
Supervision: RMU Kakanj d.o.o. Kakanj